Project Cost Management

        Ensure that the project is completed within budget
        Concerned with cost of resources needed to complete activities; consider effect of project decisions on cost of using product “life-cycle costing”



(Click above for PMBOK4 Article)


        Most prospective financial impact of using the product is outside the project scope
        Consider information needs of stakeholders, controllable and uncontrollable costs (budget separately for reward and recognition systems)
        Estimating should be based on WBS to improve accuracy
        Estimating should be done by the person performing the work
        Having historical records is key to improving estimates
        Costs (schedule, scope, resources) should be managed to estimates
        A cost (schedule, scope, baseline) should be kept and not changed
        Plans should be revised as necessary during completion of work
        Corrective action should be taken when cost problems (schedule, scope and resources) occur.
          Resource Planning:
        Determining what physical resources and quantities are needed to perform work
          Inputs to Resource Planning:
        Work Breakdown Structure
        Historical Information
        Scope Statement – justification & objectives
        Resource Pool Description – what resources are potentially available for resource planning
        Organizational Policies – staffing, procurement
        Work Breakdown Structure
        Network Diagram
        Schedule
        Risks
        Historical Information
        Scope Statement – justification & objectives
        Resource Pool Description – what resources are potentially available for resource planning
        Organizational Policies – staffing, procurement
          Resource Planning Tools & Techniques
        Expert Judgment
        Alternatives Identification
          Resource Planning Outputs:
        Resource Requirements – what type & how many resources are needed for each activity in the Work Breakdown Structure
          Cost Estimating:
        Develop approximate costs of resources
        Distinguish estimating from pricing
          Estimating – likely amount
          Pricing – business decision
        Identify alternatives and consider realigning costs in phases to their expected savings
          Cost Estimating Inputs:
        Work Breakdown Structure
        Resource Requirements
        Resource Rates (if known)
        Activity Duration Estimates
        Historical Information – (project files, commercial cost databases, team knowledge
        Chart Of Accounts – coding structure for accounting; general ledger reporting
          Cost Estimating Tools & Techniques
        Analogous Estimating – “top down”; using actual costs from previous project as basis for estimate
          Reliable when previous projects are similar and individuals have expertise – form of expert judgment
        Parametric Modeling – uses project characteristics in mathematical models to predict costs (e.g.building houses)
          Reliable when historical information is accurate, parameters are quantifiable, and model is scalable
          2 types: Regression analysis, Learning Curve
        Bottom Up Estimating – rolling up individual activities into project total – smaller work activities have more accuracy -
        Computerized tools – spreadsheets, software
        Pro’s and Con’s
        Analogous Estimating
          Quick  - Less Accurate
          Tasks don’t need to be identified – Estimates prepared with little detail and understanding of project
          Less costly – Requires considerable experience to do well
          Gives PM idea of management expectations – Infighting at high levels of organization
          Overall project costs are capped – Difficult for projects with uncertainty
        Pro’s and Con’s
        Bottom Up Estimating
          More Accurate – Takes time and expense
          Gains buy-in from the team – Tendency for team to pad estimates
          Based on detailed analysis of project – Requires that project be defined and understood
          Provides a basis for monitoring and control – Team infighting to get biggest piece of pie
          Outputs from Cost Estimating
        Cost estimates – quantitative assessments of likely costs of resources required to complete tasks
          For all resources of the project (labor, materials, supplies, inflation allowance, reserve)
          Expressed in units of currency
        Supporting Detail
          Description of scope (reference to the WBS)
          Documentation how estimate was developed
          Indication of range of possible results
          Assumptions
        Cost Management Plan – how cost variances will be managed
        Cost Risk: associated to seller for Fixed Price; associated to buyer for Time and Materials budget
          Cost Budgeting
        Involves allocation of total estimate to individual work to establish a cost baseline to measure performance
          Cost Budgeting Inputs
        Cost Estimate
        Work Breakdown Structure
        Project Schedule – includes planned start and finish dates for items costs are allocated to
          Needed to assign costs during the time period when the actual cost will be incurred
          Cost Budgeting Tools & Techniques
         same as Cost Estimating Tools and Techniques
          Outputs from Cost Budgeting
        Cost Baseline – time phased budget to measure and monitor cost performance
          Developed by summing estimated costs by period (S curve of values vs. time)
          Larger projects have multiple baselines to measure different aspects of cost performance
          Cost Control
        Concerned with influencing factors that create changes to the cost baseline that are beneficial
        Determining that the cost baseline has changed
        Managing actual changes as they occur
          Monitor cost performance to detect variances
          Record all appropriate changes accurately in the cost baseline
          Preventing incorrect, unauthorized changes being included in the cost baseline
          Informing stakeholders of authorized changes
          Determine the “why’s” of positive and negative variances
          Integrated will all other control processes (scope, change, schedule, quality)
          Inputs to Cost Control
        Cost Baseline
        Performance Reports – meet, exceed budget
          50/50 Rule – task is considered 50% complete when it begins and gets credit for remainder 50% only when completed
          20/80 Rule - task is considered 20% complete when it begins and gets credit for remainder 80% only when completed
          0/100 Rule – task only credited when fully completed
        Change Requests
        Cost Management Plan
          Tools & Techniques of Cost Control
        Cost Change Control System – defines the procedures by which the cost baseline may be changed
        Performance Measurement – assess magnitude of cost variations (Earned Value Analysis) and what is causing the variance
        Additional Planning – examine alternatives
        Computerized Tools – forecast planned costs, track actual costs, forecast effect of cost changes
          Cost Control Outputs
        Revised Cost Estimate
          Modifications to cost information; require stakeholder approval and adjustments to other project areas
        Budget Updates – changes to approved cost baseline; revised in response to scope changes
        Corrective Action
        Estimate at completion – (EAC) – forecast of total expenditures
          Actual to date plus remaining budget modified by a factor (cost performance index)
          Current variances are seen to apply to future variances
          Actual to date plus new estimate for remaining work
          Original estimates are flawed, or no longer relevant
          Actual to date plus remaining budget
          Current variances are typical and similar variances will not occur in the future
        Lessons Learned
          Earned Value Analysis
        Integrates cost, schedule and scope
        Better that comparing projected vs. actual because time and cost are analyzed separately
        Terms:
          BCWS – Budgeted Cost of Work Scheduled (how much work should be done)
          BCWP – Budgeted Cost of Work Performed a.k.a. Earned Value (how much work is budgeted, how much did we budget)
          ACWP – Actual Cost of Work Performed (how much did the completed work cost)
        Terms:
          BAC – Budget at Completion (how much did you budget for the total job)
          EAC – Estimate at Completion (what do we expect the total project to cost)
          ETC – Estimate to Completion (how much more do we expect to spend to finish the job)
          VAC – Variance at Completion (how much over/under budget do we expect to be)
        Formulas
          Variance (Plan – Actual)
          Cost Variance (CV): BCWP – ACWP; negative is over budget
          Schedule Variance (SV): BCWP – BCWS; negative is behind schedule
          Cost Performance Index (CPI):      BCWP
                                           ACWP                   
          I am only getting x¢ out of every $
        Formulas
          Schedule Performance Index (SPI): BCWP
                                            BCWS
        I am only progressing x % of the planned rate
          Estimate at Completion (EAC): BAC
                                       CPI        
        As of now we expect the total project to cost x$
          Estimate to Complete (ETC): EAC – ACWP; how much will it cost from now to completion
          Variance at Completion: BAC – EAC; when the project is over how much more or less did we spend (most common way of calculating EVA
        BCWP comes first in most formulas
        If it is a variance, BCWP comes first
        If it is an index, BCWP is divided by
        If the formula relates to cost, use AWCP
        If the formula related to schedule, use BWCP
        Negative is bad; positive results are good
        ETC refers to “this point on”; EAC refers to when job is completed
        Accuracy of Estimates
        Order of Magnitude Estimate: -25% - 75%; usually made during Initiation Phase
        Budget Estimate: -10% - 25%; usually made during the Planning phase
        Definitive Estimate: -5% - 10%; usually made during the Planning phase
        Accounting Standards
        Not usually part of the exam
        Present Value (value today of future cash flows):
          PV = FV
      (1 + r) N
FV = Future Value
R = Interest Rate
N = Number of time periods
        Net Present Value: total benefits (income or revenue) less the costs. NPV is the sum of each present value of each income/revenue item 
        Internal Rate of Return (IRR): company may select project based on highest IRR
        Payback Period: number of time periods it takes to recover the investment in the project before generating revenues
        Benefit Cost Ratio (BCR): compares costs to the benefits of different projects
          Greater than 1 means benefits are greater than costs
          Less than 1 means costs are greater than benefits
        Opportunity Cost: opportunity given up by selecting one project over another
        Sunk Costs: expended costs. Sunk costs should not be considered when determining to continue with a troubled project
        Law of Diminishing Returns: the more that is put in the less of an outcome is received
        Working Capital: current assets – current liabilities
        Variable Cost: costs that change with the amount of production or the amount of work (materials, wages)
        Fixed Cost: non-recurring costs that do not change
        Direct Cost: directly attributable to project work (travel, wages, materials)
        Indirect Cost: overhead items or costs for the benefit of more than one project (taxes, fringe benefits)
        Depreciation: assets lose value over time
          Straight Line depreciation: same amount is taken each year
          Accelerated Depreciation: 2 forms
          Double Declining Balance
          Sum of the Years Digits
        Life Cycle Costing: includes operations and maintenance phases
        Value Analysis: find a less costly way to do same work
        Make or Buy decisions –at Development (Planning) phase, not conceptual phase
        Project Objectives – are not necessarily needed to fund project
        Project Definition – focus on end product initially; costs and benefits will be evaluated later
        25% of project lifecycle expended at end of planning
        No guarantees; only most likely results
        Line of Balance charts are used for manufacturing
        Negative Float – the late start date is earlier than the early start date
        Value Engineering/analysis – does not trade performance for cost
        Prospectus – profitability and technical feasibility used to solicit funding
        Definitive Estimate –most precise/accurate estimate for determining project costs
        Management Reserve – over time PM wants no change to reserve; customers wants $ back
        Cost and Schedule Data – predicts future performance
        ROI, Nest Present Value and Discounted Cash Flow – all can be used to measure total income vs. total $ expended
        Undistributed budget – budget that contains approved scope changes but are not planned yet
        Depreciation is not a measurement of profitability
        Pay Back Period - # of periods required to recover the initial investment