Project Cost Management

–        Ensure that the project is completed within budget
–        Concerned with cost of resources needed to complete activities; consider effect of project decisions on cost of using product “life-cycle costing”



(Click above for PMBOK4 Article)


–        Most prospective financial impact of using the product is outside the project scope
–        Consider information needs of stakeholders, controllable and uncontrollable costs (budget separately for reward and recognition systems)
–        Estimating should be based on WBS to improve accuracy
–        Estimating should be done by the person performing the work
–        Having historical records is key to improving estimates
–        Costs (schedule, scope, resources) should be managed to estimates
–        A cost (schedule, scope, baseline) should be kept and not changed
–        Plans should be revised as necessary during completion of work
–        Corrective action should be taken when cost problems (schedule, scope and resources) occur.
•          Resource Planning:
–        Determining what physical resources and quantities are needed to perform work
•          Inputs to Resource Planning:
–        Work Breakdown Structure
–        Historical Information
–        Scope Statement – justification & objectives
–        Resource Pool Description – what resources are potentially available for resource planning
–        Organizational Policies – staffing, procurement
–        Work Breakdown Structure
–        Network Diagram
–        Schedule
–        Risks
–        Historical Information
–        Scope Statement – justification & objectives
–        Resource Pool Description – what resources are potentially available for resource planning
–        Organizational Policies – staffing, procurement
•          Resource Planning Tools & Techniques
–        Expert Judgment
–        Alternatives Identification
•          Resource Planning Outputs:
–        Resource Requirements – what type & how many resources are needed for each activity in the Work Breakdown Structure
•          Cost Estimating:
–        Develop approximate costs of resources
–        Distinguish estimating from pricing
•          Estimating – likely amount
•          Pricing – business decision
–        Identify alternatives and consider realigning costs in phases to their expected savings
•          Cost Estimating Inputs:
–        Work Breakdown Structure
–        Resource Requirements
–        Resource Rates (if known)
–        Activity Duration Estimates
–        Historical Information – (project files, commercial cost databases, team knowledge
–        Chart Of Accounts – coding structure for accounting; general ledger reporting
•          Cost Estimating Tools & Techniques
–        Analogous Estimating – “top down”; using actual costs from previous project as basis for estimate
•          Reliable when previous projects are similar and individuals have expertise – form of expert judgment
–        Parametric Modeling – uses project characteristics in mathematical models to predict costs (e.g.building houses)
•          Reliable when historical information is accurate, parameters are quantifiable, and model is scalable
•          2 types: Regression analysis, Learning Curve
–        Bottom Up Estimating – rolling up individual activities into project total – smaller work activities have more accuracy -
–        Computerized tools – spreadsheets, software
–        Pro’s and Con’s
–        Analogous Estimating
•          Quick  - Less Accurate
•          Tasks don’t need to be identified – Estimates prepared with little detail and understanding of project
•          Less costly – Requires considerable experience to do well
•          Gives PM idea of management expectations – Infighting at high levels of organization
•          Overall project costs are capped – Difficult for projects with uncertainty
–        Pro’s and Con’s
–        Bottom Up Estimating
•          More Accurate – Takes time and expense
•          Gains buy-in from the team – Tendency for team to pad estimates
•          Based on detailed analysis of project – Requires that project be defined and understood
•          Provides a basis for monitoring and control – Team infighting to get biggest piece of pie
•          Outputs from Cost Estimating
–        Cost estimates – quantitative assessments of likely costs of resources required to complete tasks
•          For all resources of the project (labor, materials, supplies, inflation allowance, reserve)
•          Expressed in units of currency
–        Supporting Detail
•          Description of scope (reference to the WBS)
•          Documentation how estimate was developed
•          Indication of range of possible results
•          Assumptions
–        Cost Management Plan – how cost variances will be managed
–        Cost Risk: associated to seller for Fixed Price; associated to buyer for Time and Materials budget
•          Cost Budgeting
–        Involves allocation of total estimate to individual work to establish a cost baseline to measure performance
•          Cost Budgeting Inputs
–        Cost Estimate
–        Work Breakdown Structure
–        Project Schedule – includes planned start and finish dates for items costs are allocated to
•          Needed to assign costs during the time period when the actual cost will be incurred
•          Cost Budgeting Tools & Techniques
–         same as Cost Estimating Tools and Techniques
•          Outputs from Cost Budgeting
–        Cost Baseline – time phased budget to measure and monitor cost performance
•          Developed by summing estimated costs by period (S curve of values vs. time)
•          Larger projects have multiple baselines to measure different aspects of cost performance
•          Cost Control
–        Concerned with influencing factors that create changes to the cost baseline that are beneficial
–        Determining that the cost baseline has changed
–        Managing actual changes as they occur
•          Monitor cost performance to detect variances
•          Record all appropriate changes accurately in the cost baseline
•          Preventing incorrect, unauthorized changes being included in the cost baseline
•          Informing stakeholders of authorized changes
•          Determine the “why’s” of positive and negative variances
•          Integrated will all other control processes (scope, change, schedule, quality)
•          Inputs to Cost Control
–        Cost Baseline
–        Performance Reports – meet, exceed budget
•          50/50 Rule – task is considered 50% complete when it begins and gets credit for remainder 50% only when completed
•          20/80 Rule - task is considered 20% complete when it begins and gets credit for remainder 80% only when completed
•          0/100 Rule – task only credited when fully completed
–        Change Requests
–        Cost Management Plan
•          Tools & Techniques of Cost Control
–        Cost Change Control System – defines the procedures by which the cost baseline may be changed
–        Performance Measurement – assess magnitude of cost variations (Earned Value Analysis) and what is causing the variance
–        Additional Planning – examine alternatives
–        Computerized Tools – forecast planned costs, track actual costs, forecast effect of cost changes
•          Cost Control Outputs
–        Revised Cost Estimate
•          Modifications to cost information; require stakeholder approval and adjustments to other project areas
–        Budget Updates – changes to approved cost baseline; revised in response to scope changes
–        Corrective Action
–        Estimate at completion – (EAC) – forecast of total expenditures
•          Actual to date plus remaining budget modified by a factor (cost performance index)
•          Current variances are seen to apply to future variances
•          Actual to date plus new estimate for remaining work
•          Original estimates are flawed, or no longer relevant
•          Actual to date plus remaining budget
•          Current variances are typical and similar variances will not occur in the future
–        Lessons Learned
•          Earned Value Analysis
–        Integrates cost, schedule and scope
–        Better that comparing projected vs. actual because time and cost are analyzed separately
–        Terms:
•          BCWS – Budgeted Cost of Work Scheduled (how much work should be done)
•          BCWP – Budgeted Cost of Work Performed a.k.a. Earned Value (how much work is budgeted, how much did we budget)
•          ACWP – Actual Cost of Work Performed (how much did the completed work cost)
–        Terms:
•          BAC – Budget at Completion (how much did you budget for the total job)
•          EAC – Estimate at Completion (what do we expect the total project to cost)
•          ETC – Estimate to Completion (how much more do we expect to spend to finish the job)
•          VAC – Variance at Completion (how much over/under budget do we expect to be)
–        Formulas
•          Variance (Plan – Actual)
•          Cost Variance (CV): BCWP – ACWP; negative is over budget
•          Schedule Variance (SV): BCWP – BCWS; negative is behind schedule
•          Cost Performance Index (CPI):      BCWP
                                           ACWP                   
•          I am only getting x¢ out of every $
–        Formulas
•          Schedule Performance Index (SPI): BCWP
                                            BCWS
–        I am only progressing x % of the planned rate
•          Estimate at Completion (EAC): BAC
                                       CPI        
–        As of now we expect the total project to cost x$
•          Estimate to Complete (ETC): EAC – ACWP; how much will it cost from now to completion
•          Variance at Completion: BAC – EAC; when the project is over how much more or less did we spend (most common way of calculating EVA
–        BCWP comes first in most formulas
–        If it is a variance, BCWP comes first
–        If it is an index, BCWP is divided by
–        If the formula relates to cost, use AWCP
–        If the formula related to schedule, use BWCP
–        Negative is bad; positive results are good
–        ETC refers to “this point on”; EAC refers to when job is completed
–        Accuracy of Estimates
–        Order of Magnitude Estimate: -25% - 75%; usually made during Initiation Phase
–        Budget Estimate: -10% - 25%; usually made during the Planning phase
–        Definitive Estimate: -5% - 10%; usually made during the Planning phase
–        Accounting Standards
–        Not usually part of the exam
–        Present Value (value today of future cash flows):
•          PV = FV
      (1 + r) N
FV = Future Value
R = Interest Rate
N = Number of time periods
–        Net Present Value: total benefits (income or revenue) less the costs. NPV is the sum of each present value of each income/revenue item 
–        Internal Rate of Return (IRR): company may select project based on highest IRR
–        Payback Period: number of time periods it takes to recover the investment in the project before generating revenues
–        Benefit Cost Ratio (BCR): compares costs to the benefits of different projects
•          Greater than 1 means benefits are greater than costs
•          Less than 1 means costs are greater than benefits
–        Opportunity Cost: opportunity given up by selecting one project over another
–        Sunk Costs: expended costs. Sunk costs should not be considered when determining to continue with a troubled project
–        Law of Diminishing Returns: the more that is put in the less of an outcome is received
–        Working Capital: current assets – current liabilities
–        Variable Cost: costs that change with the amount of production or the amount of work (materials, wages)
–        Fixed Cost: non-recurring costs that do not change
–        Direct Cost: directly attributable to project work (travel, wages, materials)
–        Indirect Cost: overhead items or costs for the benefit of more than one project (taxes, fringe benefits)
–        Depreciation: assets lose value over time
•          Straight Line depreciation: same amount is taken each year
•          Accelerated Depreciation: 2 forms
•          Double Declining Balance
•          Sum of the Years Digits
–        Life Cycle Costing: includes operations and maintenance phases
–        Value Analysis: find a less costly way to do same work
–        Make or Buy decisions –at Development (Planning) phase, not conceptual phase
–        Project Objectives – are not necessarily needed to fund project
–        Project Definition – focus on end product initially; costs and benefits will be evaluated later
–        25% of project lifecycle expended at end of planning
–        No guarantees; only most likely results
–        Line of Balance charts are used for manufacturing
–        Negative Float – the late start date is earlier than the early start date
–        Value Engineering/analysis – does not trade performance for cost
–        Prospectus – profitability and technical feasibility used to solicit funding
–        Definitive Estimate –most precise/accurate estimate for determining project costs
–        Management Reserve – over time PM wants no change to reserve; customers wants $ back
–        Cost and Schedule Data – predicts future performance
–        ROI, Nest Present Value and Discounted Cash Flow – all can be used to measure total income vs. total $ expended
–        Undistributed budget – budget that contains approved scope changes but are not planned yet
–        Depreciation is not a measurement of profitability
–        Pay Back Period - # of periods required to recover the initial investment