•
Project
Integration Management
–
Ensures
that the project processes are properly coordinated
–
Tradeoffs
between competing objectives and alternatives in order to meet stakeholder
approval
(Click
above for PMBOK4 Article)
•
Project
Plan Development
•
Project
Plan Execution
•
Overall
Change Control
–
These
processes may occur repeatedly over the project duration
–
Historical
Records are needed to perform project management well, they are inputs to
continuous improvement
•
Files
•
Lessons
Learned
•
Actual
Costs
•
Time
Estimates
•
WBS
•
Benchmarks
•
Risks
•
Project
Plan Development
–
Uses
outputs from other planning processes to create consistent document to guide
project execution and control
–
Iterated
several times
–
Documents
planning assumptions
–
Documents
planning decisions that are chosen
–
Facilitates
communication
–
Defines
key management reviews
–
Provides
a baseline to track progress measurement and project control
•
Project
Plan Development Inputs
–
Other
planning outputs: primarily the planning process outputs (WBS, base documents,
application area inputs)
–
Historical
information – verify assumptions, records of past project performance
–
Organizational
policies – quality management, personnel administration, Financial controls
–
Constraints
– factors that limit performance, contractual provisions, budget
–
Assumptions
– risk factors
•
Tools
& Techniques for Plan Development
–
Project
Planning Methodology – any structured approach (software, templates, forms,
start-up meetings
–
Stakeholder
Skills & Knowledge – tap into plan development; use expertise for
reasonableness
–
PMIS
– Out of the box approach to support all project aspects through closure
•
Project
Plan Development Outputs
–
Project
Plan is a collection that changes over time as more information about the
project becomes available
–
Baseline
will change only in response to approved scope change
–
Project
Plan includes some or all of the following:
•
Project
Charter
•
Project
Management approach or strategy
•
Scope
statement
•
Work
Breakdown Structure (WBS)
•
Budget,
schedule, risks
•
Key
Staff, Major Milestones
•
Change
Control Plan, Management and Communications Plan
•
Cost
Estimates, scheduled start dates and responsibility assignments
•
Performance
measurement baselines
•
Major
milestones and target dates
•
Required
Staff
•
Risks,
constraints and assumptions
•
Subsidiary
management plans (scope, schedule)
•
Open
Issues
•
Pending
Decisions
•
Supporting
Details to the Project Plan
–
Outputs
from planning processes
–
Technical
documentation
–
Business
requirements, specifications, and designs
–
Relevant
standards
–
Additional
information not previously known
•
Project
Plan Execution
–
Primary
process for carrying out the project plan
–
Most
costly aspect of project management
–
Direction
of organizational resources and interfaces
•
Project
Plan Execution Inputs:
–
Project
Plan
–
Supporting
Detail
–
Organizational
Policies
–
Corrective
Action – anything to bring expected performance in line with the project plan
•
Tools
& Techniques for Plan Execution
–
General
Management Skills
–
Product
Skills and Knowledge – defined as part of planning, provided by staffing
–
Work
Authorization System – formal procedure for sanctioning work to ensure
completion – written or verbal authorization
–
Status
review meetings – regular exchanges of information
–
Project
Management Information System
–
Organizational
Procedures
•
Project
Plan Execution Outputs
–
Work
results – the outcome of activities performed is fed into the performance
reporting process
–
Change
Requests – expand/shrink project scope, modify costs and schedule estimates
•
Overall
Change Control
–
Influencing
factors that create change to ensure beneficial results; ensure that change is
beneficial
–
Determining
that change has occurred
–
Managing
actual changes as they occur
•
Evaluate
impact of change
•
Meet
with team to discuss alternatives
•
Meet
with management to present decision
•
Change
control requires
–
Maintaining
integrity of performance measurement baselines (project plan)
–
Ensuring
changes to scope are accurately recorded
–
Coordinating
changes across knowledge areas (scheduling, risk, cost, quality, etc.)
–
Determine
all factors that control change and pro-actively preventing the occurrence;
evaluate the impact of change
•
Inputs
to Change Control
–
Project
Plan – baseline performance
–
Performance
Reports – issue tracking, risk management
–
Change
Requests – orally or written, externally or internally initiates, legally
mandated or optional
•
Change
Control Tools & Techniques
–
All
Changes must be evaluated before a decision can be reached
–
Change
Control System – collection of formal procedures, paperwork, tracking systems,
approval levels
–
Change
Control Board – decision making authority
–
Configuration
Management – documented procedure to apply technical and administrative
direction
•
ID
and document functional and physical characteristics
•
Control
changes to these characteristics
•
Record
and report change and implementation status
•
Audit
items and system to verify requirements
•
Change
Control Tools & Techniques
–
Performance
Measurement – earned value, plan variance analysis
–
Additional
Planning – revised cost estimates, modify activity sequences, plan adjustments
–
Project
Management Information System
–
Change
Control System may have
•
Change
Control Plan
•
Change
Control Board
•
Change
Control Procedures, Corrective Action plans
•
Performance
Statistics, Reports, Change forms
•
Specification
reviews, Demonstrations, Testing, Meetings
–
Configuration
Management
•
Change
Control Outputs
–
Project
Plan Updates
–
Corrective
Actions
–
Lessons
Learned – variance causes and reasoning documented for historical purposes
•
Configuration
Management
–
Rigorous
Change Management as it relates to scope
•
Subset
of the change control system
•
Work
Authorization System
–
Controls
“gold plating”; defines what task is/is not
•
Meetings
–
Most
are inefficient; keep minutes
–
Status
can be determined without meeting
•
Lessons
Learned
–
Project
is not complete until a Lessons Learned is completed
–
What
have we done, how can we do it better
•
Technical
Aspects of the project
•
Project
Management (WBS, plans, etc.)
•
Overall
Management (communications, leadership)
•
Best
to have whole team complete and made available
•
Also
called “Post – Mortem”
•
Integration
is a result of need for communication within a project
•
Primary
responsibility to decide what changes are necessary is Management
•
Project
Managers must pro-actively define and solve problems before reporting to
superiors