Project Integration Management

          Project Integration Management
        Ensures that the project processes are properly coordinated
        Tradeoffs between competing objectives and alternatives in order to meet stakeholder approval



(Click above for PMBOK4 Article)


          Project Plan Development
          Project Plan Execution
          Overall Change Control
        These processes may occur repeatedly over the project duration
        Historical Records are needed to perform project management well, they are inputs to continuous improvement
          Files
          Lessons Learned
          Actual Costs
          Time Estimates
          WBS
          Benchmarks
          Risks
          Project Plan Development
        Uses outputs from other planning processes to create consistent document to guide project execution and control
        Iterated several times
        Documents planning assumptions
        Documents planning decisions that are chosen
        Facilitates communication
        Defines key management reviews
        Provides a baseline to track progress measurement and project control
          Project Plan Development Inputs
        Other planning outputs: primarily the planning process outputs (WBS, base documents, application area inputs)
        Historical information – verify assumptions, records of past project performance
        Organizational policies – quality management, personnel administration, Financial controls
        Constraints – factors that limit performance, contractual provisions, budget
        Assumptions – risk factors
          Tools & Techniques for Plan Development
        Project Planning Methodology – any structured approach (software, templates, forms, start-up meetings
        Stakeholder Skills & Knowledge – tap into plan development; use expertise for reasonableness
        PMIS – Out of the box approach to support all project aspects through closure
          Project Plan Development Outputs
        Project Plan is a collection that changes over time as more information about the project becomes available
        Baseline will change only in response to approved scope change
        Project Plan includes some or all of the following:
          Project Charter
          Project Management approach or strategy
          Scope statement
          Work Breakdown Structure (WBS)
          Budget, schedule, risks
          Key Staff, Major Milestones
          Change Control Plan, Management and Communications Plan
          Cost Estimates, scheduled start dates and responsibility assignments
          Performance measurement baselines
          Major milestones and target dates
          Required Staff
          Risks, constraints and assumptions
          Subsidiary management plans (scope, schedule)
          Open Issues
          Pending Decisions
          Supporting Details to the Project Plan
        Outputs from planning processes
        Technical documentation
        Business requirements, specifications, and designs
        Relevant standards
        Additional information not previously known
          Project Plan Execution
        Primary process for carrying out the project plan
        Most costly aspect of project management
        Direction of organizational resources and interfaces
          Project Plan Execution Inputs:
        Project Plan
        Supporting Detail
        Organizational Policies
        Corrective Action – anything to bring expected performance in line with the project plan
          Tools & Techniques for Plan Execution
        General Management Skills
        Product Skills and Knowledge – defined as part of planning, provided by staffing
        Work Authorization System – formal procedure for sanctioning work to ensure completion – written or verbal authorization
        Status review meetings – regular exchanges of information
        Project Management Information System
        Organizational Procedures
          Project Plan Execution Outputs
        Work results – the outcome of activities performed is fed into the performance reporting process
        Change Requests – expand/shrink project scope, modify costs and schedule estimates
          Overall Change Control
        Influencing factors that create change to ensure beneficial results; ensure that change is beneficial
        Determining that change has occurred
        Managing actual changes as they occur
          Evaluate impact of change
          Meet with team to discuss alternatives
          Meet with management to present decision
          Change control requires
        Maintaining integrity of performance measurement baselines (project plan)
        Ensuring changes to scope are accurately recorded
        Coordinating changes across knowledge areas (scheduling, risk, cost, quality, etc.)
        Determine all factors that control change and pro-actively preventing the occurrence; evaluate the impact of change
          Inputs to Change Control
        Project Plan – baseline performance
        Performance Reports – issue tracking, risk management
        Change Requests – orally or written, externally or internally initiates, legally mandated or optional
          Change Control Tools & Techniques
        All Changes must be evaluated before a decision can be reached
        Change Control System – collection of formal procedures, paperwork, tracking systems, approval levels
        Change Control Board – decision making authority
        Configuration Management – documented procedure to apply technical and administrative direction
          ID and document functional and physical characteristics
          Control changes to these characteristics
          Record and report change and implementation status
          Audit items and system to verify requirements
          Change Control Tools & Techniques
        Performance Measurement – earned value, plan variance analysis
        Additional Planning – revised cost estimates, modify activity sequences, plan adjustments
        Project Management Information System
        Change Control System may have
          Change Control Plan
          Change Control Board
          Change Control Procedures, Corrective Action plans
          Performance Statistics, Reports, Change forms
          Specification reviews, Demonstrations, Testing, Meetings
        Configuration Management
          Change Control Outputs
        Project Plan Updates
        Corrective Actions
        Lessons Learned – variance causes and reasoning documented for historical purposes
          Configuration Management
        Rigorous Change Management as it relates to scope
          Subset of the change control system
          Work Authorization System
        Controls “gold plating”; defines what task is/is not
          Meetings
        Most are inefficient; keep minutes
        Status can be determined without meeting
          Lessons Learned
        Project is not complete until a Lessons Learned is completed
        What have we done, how can we do it better
          Technical Aspects of the project
          Project Management (WBS, plans, etc.)
          Overall Management (communications, leadership)
          Best to have whole team complete and made available
          Also called “Post – Mortem”
          Integration is a result of need for communication within a project
          Primary responsibility to decide what changes are necessary is Management
          Project Managers must pro-actively define and solve problems before reporting to superiors